Large construction site Ellerried: Traffic chaos in Schwerin until the end of August!

Large construction site Ellerried: Traffic chaos in Schwerin until the end of August!
Ellerried, Schwerin, Deutschland - In Schwerin, the citizens are: inside a big change. From June 16, comprehensive repair work on Ellerried street, which will probably continue until August 29, 2025, will begin, as Schwerin-Lokal . This work concerns both the road and bus stops to improve the city's infrastructure.
The measures are carried out by the urban self -operating SDS and are divided into several construction phases in order to keep traffic disabilities as low as possible. At the same time, the traffic at the B106 / Ellerried junction is regulated by a light signal system, which is supposed to facilitate the passage for drivers: on the inside. The access to the popular seven-sea center remains guaranteed at all times via Grabenstraße.
construction phases and traffic tours
The construction work is carried out in a total of three sections:
- construction phase 3: from June 16 to 27, there is a section of the full closure between house numbers 9 and 15. In the period from June 30th to July 4th, the area between the Eckdrift / Ellerried and house number 15 intersection will be closed. This is followed by a complete blocking for asphalting from July 7th to 11th, which also includes access to the B106.
- construction phase 2: From 14 July to August 22nd, full closures between the intersection Eckdrift/Ellerried and house number 41 are planned, with holding and parking bans in this area.
- construction phase 1: from August 4th to 22nd, there will be a traffic routing via the traffic light system in addition to a half -side closure.
The final full closure between Grabenstraße and the intersection Eckdrift / Ellerried takes place from August 25th to 29th to complete the asphalting in the first two construction phases. During this time, a bus reduction is set up, so that the stops such as "Zum Schulacker" on the bypass and the stops towards the main train station and Göries/Lankow settlement are approached outside the construction area.
traffic information in real time
For everyone who is on the road during this time, the ADAC offers a practical overview of the traffic flow and possible disorders with its ADAC MAPS . The platform not only shows the current traffic situations on motorways and federal roads, but also provides information about planned construction sites as well as dangerous situations such as smoothness or storm warnings. This digital solution can be valuable help to avoid delays.
Finally, it is important to mention that the Ellerried construction site is not isolated. Germany is currently involved in many different major projects that shape the building. For example, Planradar , for example, of impressive construction projects such as the Fehmarnbelt-Tunnel 21, which all aim to improve the infrastructure in our country and to promote mobility.The changes in the Ellerried street are therefore part of a larger image that unfolds in Germany. Even if there can be restrictions during the construction period, the measures for the future of our city are of great importance.