Concert pavilion in Malchin: Piles too short - construction is delayed!

Im Malchiner Stadtpark verzögert sich der Bau eines Konzertpavillons wegen unzureichender Pfahlgründung. Bürgermeister informiert.
In the Malchiner city park, the construction of a concert pavilion is delayed due to inadequate pile foundation. Mayor informed. (Symbolbild/MMV)

Concert pavilion in Malchin: Piles too short - construction is delayed!

The plans for the new concert pavilion in the Malchin city park have stalled. Mayor Axel Müller (CDU) recently informed about unexpected problems in building, which are due to the foundation of the pile. This was brought in by the commissioned company, but the piles used are provided with insufficient load -bearing capacity, so that an extension is now required. This measure is already being prepared, but it is unclear how long the completion of the pavilion will be delayed, since there are no exact time frames.

The strict requirements of the approval authorities have led to the statics of the foundation being particularly closely examined. The upgrading of the park and the creation of a meeting point for young people are still the goal, so that the city administration actively concerns the problem situation. However, the opening of a new playground was celebrated, which has already been well received. New benches and wastebasket were also set up in the area - steps that should make the city park even more attractive.

bridge over the Mühlenteich

There is also another construction site in the community: The bridge at the Mühlenteich, which has been blocked for weeks, is waiting for its release. The city has already advertised repair work after the funding has been approved. The Malchiners hope that the bridge will soon be fully accessible again, because the state causes resentment among the residents.

pile foundations, such as those now used in the city park, are helpful technologies to safely derive building lights in sustainable soil layers. This special type of foundation is used primarily when the building ground is insufficiently viable. Piles have proven themselves for thousands of years and are now used in a wide variety of shapes and materials to meet the specific requirements of the construction project. The penetration into the floor and filling with concrete, as with bored piles, is a common method that could also be used in Malchin to increase the load -bearing capacity.

The discussion about pile foundations is not new. Experts warn that the dismantling obligation for such foundations is legally unclear and that technical challenges entail. Complete dismantling could also result in considerable interventions in the soil structure. It is therefore advisable to illuminate the purpose of a dismantling obligation in the dialogue with the responsible authorities and check out possibly favored options in order to avoid future difficulties.

In summary, the Malchin city park is facing an exciting development, even if the challenges in building the concert pavilion and the bridge are currently in the foreground. The city relies on improvements that increase both the attractiveness and the uses for citizens.

Nordkurier reports on the developments, while Wind Industry in Germany offers a broader overview of pile foundations. In addition, tensar corp. available information about the history and use of pile foundations.